Town Hall with Priland
- Time
- 4:16 PM to 6:22 PM
- Venue
- Breeza Coves Clubhouse
- Attendance
- 31 (6 officers, 25 homeowners)
Summary
Homeowners met with Priland to discuss the cemented open area and common spaces, the emergency deep well, the entrance gate light, drainage and detention ponds, Phase 2 electricity, mud and trucks on Phase 1 roads, the concerns process, pets and stray cats, HOA group chats and the Christmas party.
Key Decisions
- Deep well will be an HOA project (quotes by Nov 30, proposal by Dec 15).
- Agreement with Priland on the cemented open area cost (by Nov 13).
- Entrance gate light follow-up Nov 13, repainting Nov 27.
- A new concerns process with the PMO (by Nov 11).
- Christmas party polls for date and food (by Nov 16).
Full Minutes
| Date | Saturday, 7 November 2026 |
| Venue | Breeza Coves Clubhouse |
| Time Started | 4:16 PM |
| Time Ended | 6:22 PM |
| Meeting Type | Town Hall |
| Attendance | 31 (6 officers, 25 homeowners) |
Attendance
31 attendees · 6 officers / Board of Directors · 25 homeowners and representatives
Names are not included in this public copy. The signed attendance sheet is on file with the HOA Secretary.
1. Cemented Open Area and Common Spaces
Discussion
-
The site development plan can only be obtained after the common areas are turned over to the HOA.
-
The HOA will request a copy of the site development plan from Rob (Priland), to check if the 30% open space is in line with the law.
-
The BOD, the HOA and Priland will sign an agreement on Priland's commitment to cover the cost of the cemented open area.
-
Upon turnover of the common spaces, the HOA will ask Priland to provide the playground equipment shown in the marketing brochures.
-
Clubhouse: the gutter is already rusted and needs repair by Priland engineering. The HOA will prepare a punch list of items to request, based on Priland's marketing materials.
| Action Item | Responsible | Timeline |
|---|---|---|
| Request a copy of the site development plan from Rob (Priland) | HOA BOD | Nov 10, 2026 |
| Draft the agreement on Priland covering the cost of the cemented open area | HOA BOD with Priland | Nov 13, 2026 |
| Prepare the punch list (playground equipment, clubhouse gutter, other items from the marketing materials) | HOA BOD | April 2027 |
| Get a timeline for the cemented area and the common space turnover | HOA BOD with Priland | December 2026 |
2. Emergency Deep Well
Discussion
-
The deep well will be a project of the HOA.
-
The HOA needs quotations from contractors who will do the deep well work.
-
A full proposal is needed, including the price, maintenance, and the reasons for the project.
-
The Deed of Restrictions will be posted in the Facebook group.
| Action Item | Responsible | Timeline |
|---|---|---|
| Get quotations from deep well contractors | HOA BOD | Nov 30, 2026 |
| Prepare the full deep well proposal (price, maintenance, reasons) | Secretary with BOD | Dec 15, 2026 |
| Post the Deed of Restrictions in the Facebook group | Secretary | Nov 13, 2026 |
| Set a project timeline | HOA BOD | January 2027 |
3. Entrance Gate Light and Repainting
Discussion
-
The entrance gate light is approved. Waiting for the PD to schedule the installation.
-
The entrance gate will also be repainted.
| Action Item | Responsible | Timeline |
|---|---|---|
| Follow up with the PD on the light installation schedule | HOA BOD | Nov 13, 2026 |
| Follow up on the gate repainting schedule | HOA BOD | Nov 27, 2026 |
| Complete the gate light installation and repainting | HOA BOD with Priland | Dec 15, 2026 |
4. Phase 2 Update
Discussion
-
A building is needed before MECO can approve the electricity connection for Phase 2, including power for the pump at detention pond 2.
-
The mud issue was raised before, but no solution has been given. Issues seem to be reported but not acted on.
-
Big trucks pass through and park in the subdivision, which is not safe for children.
-
Issue raised: the elevated area in Phase 2.
| Action Item | Responsible | Timeline |
|---|---|---|
| Follow up with Priland on the MECO connection and the pump for detention pond 2 | HOA BOD | December 2026 |
| Follow up on the mud issue and get a concrete solution | HOA BOD with Priland | Nov 13, 2026 |
| Raise truck passing and parking rules for safety | HOA BOD with Priland | Nov 30, 2026 |
| Get Priland's response on the elevated area in Phase 2 | HOA BOD | December 2026 |
5. Concerns System
Discussion
-
The HOA created a concerns system with the PMO for action tracking and timelines.
-
Concerns are being reported but not acted on, which has been disappointing. A better process with the PMO is needed.
| Action Item | Responsible | Timeline |
|---|---|---|
| Agree with the PMO on response times and regular status updates for logged concerns | HOA BOD with PMO | Nov 11, 2026 |
6. Drainage and Grass Near the Detention Pond
Discussion
-
The drainage near the detention pond is sometimes clogged with dirt during rain. A homeowner asked who is in charge of maintaining and clearing the drainage.
-
Grass is growing in front of Block 3 along the detention pond area. Sir Lourd suggested cementing the area so grass will not grow back.
-
A maintenance officer needs to be identified.
| Action Item | Responsible | Timeline |
|---|---|---|
| Confirm who is in charge of drainage maintenance and clearing | HOA BOD with Priland | To be set |
| Assess the suggestion to cement the area in front of Block 3 | HOA BOD | To be set |
| Identify a maintenance officer | HOA BOD | To be set |
7. Dog and Stray Cat Issue
Discussion
-
November 11: the City Veterinary Office will do impounding and will speak with the dog's owner to resolve the issue.
-
If this does not work, homeowners will sign a petition requiring the dog to be leashed.
-
Stray cats: ask the City Veterinary Office if they can also collect stray cats.
| Action Item | Responsible | Timeline |
|---|---|---|
| Coordinate the November 11 visit with the City Veterinary Office | HOA BOD | Nov 11, 2026 |
| Prepare a petition if the intervention fails | Secretary | After Nov 11 |
| Ask the City Veterinary Office about stray cats | HOA BOD | Nov 11, 2026 |
8. HOA Group Chats
Discussion
- Homeowners are encouraged to join all HOA channels: the Main group chat, Marketplace, Concerns, and the Facebook group.
| Action Item | Responsible | Timeline |
|---|---|---|
| Share the links to all group chats and the Facebook group | Secretary | Nov 9, 2026 |
9. Christmas Party
Discussion
-
A poll will be created for the food: catering, potluck or packed lunch.
-
Food coupons and wristbands will be used.
-
A poll will be created for the date: Sunday, December 13 or Sunday, December 20.
-
Idea: a singing contest.
| Action Item | Responsible | Timeline |
|---|---|---|
| Create the poll for the food option | Secretary | Nov 16, 2026 |
| Create the poll for the date (Dec 13 or Dec 20) | Secretary | Nov 16, 2026 |
| Prepare food coupons and wristbands | Christmas party committee | Before the event |
10. Adjournment
There being no other matters to discuss, the meeting was adjourned at 6:22 PM.
Prepared by: Jessica Jenn M. Bordios, Secretary
Noted by: Lourd Bernard Mejares, President
Signed copy on file with the HOA Secretary.