Town Hall with Priland

Town Hall with Priland

Time
4:16 PM to 6:22 PM
Venue
Breeza Coves Clubhouse
Attendance
31 (6 officers, 25 homeowners)

Summary

Homeowners met with Priland to discuss the cemented open area and common spaces, the emergency deep well, the entrance gate light, drainage and detention ponds, Phase 2 electricity, mud and trucks on Phase 1 roads, the concerns process, pets and stray cats, HOA group chats and the Christmas party.

Key Decisions

  • Deep well will be an HOA project (quotes by Nov 30, proposal by Dec 15).
  • Agreement with Priland on the cemented open area cost (by Nov 13).
  • Entrance gate light follow-up Nov 13, repainting Nov 27.
  • A new concerns process with the PMO (by Nov 11).
  • Christmas party polls for date and food (by Nov 16).

Full Minutes

DateSaturday, 7 November 2026
VenueBreeza Coves Clubhouse
Time Started4:16 PM
Time Ended6:22 PM
Meeting TypeTown Hall
Attendance31 (6 officers, 25 homeowners)

Attendance

31 attendees  ·  6 officers / Board of Directors  ·  25 homeowners and representatives

Names are not included in this public copy. The signed attendance sheet is on file with the HOA Secretary.

1. Cemented Open Area and Common Spaces

Discussion

  • The site development plan can only be obtained after the common areas are turned over to the HOA.

  • The HOA will request a copy of the site development plan from Rob (Priland), to check if the 30% open space is in line with the law.

  • The BOD, the HOA and Priland will sign an agreement on Priland's commitment to cover the cost of the cemented open area.

  • Upon turnover of the common spaces, the HOA will ask Priland to provide the playground equipment shown in the marketing brochures.

  • Clubhouse: the gutter is already rusted and needs repair by Priland engineering. The HOA will prepare a punch list of items to request, based on Priland's marketing materials.

Action ItemResponsibleTimeline
Request a copy of the site development plan from Rob (Priland)HOA BODNov 10, 2026
Draft the agreement on Priland covering the cost of the cemented open areaHOA BOD with PrilandNov 13, 2026
Prepare the punch list (playground equipment, clubhouse gutter, other items from the marketing materials)HOA BODApril 2027
Get a timeline for the cemented area and the common space turnoverHOA BOD with PrilandDecember 2026

2. Emergency Deep Well

Discussion

  • The deep well will be a project of the HOA.

  • The HOA needs quotations from contractors who will do the deep well work.

  • A full proposal is needed, including the price, maintenance, and the reasons for the project.

  • The Deed of Restrictions will be posted in the Facebook group.

Action ItemResponsibleTimeline
Get quotations from deep well contractorsHOA BODNov 30, 2026
Prepare the full deep well proposal (price, maintenance, reasons)Secretary with BODDec 15, 2026
Post the Deed of Restrictions in the Facebook groupSecretaryNov 13, 2026
Set a project timelineHOA BODJanuary 2027

3. Entrance Gate Light and Repainting

Discussion

  • The entrance gate light is approved. Waiting for the PD to schedule the installation.

  • The entrance gate will also be repainted.

Action ItemResponsibleTimeline
Follow up with the PD on the light installation scheduleHOA BODNov 13, 2026
Follow up on the gate repainting scheduleHOA BODNov 27, 2026
Complete the gate light installation and repaintingHOA BOD with PrilandDec 15, 2026

4. Phase 2 Update

Discussion

  • A building is needed before MECO can approve the electricity connection for Phase 2, including power for the pump at detention pond 2.

  • The mud issue was raised before, but no solution has been given. Issues seem to be reported but not acted on.

  • Big trucks pass through and park in the subdivision, which is not safe for children.

  • Issue raised: the elevated area in Phase 2.

Action ItemResponsibleTimeline
Follow up with Priland on the MECO connection and the pump for detention pond 2HOA BODDecember 2026
Follow up on the mud issue and get a concrete solutionHOA BOD with PrilandNov 13, 2026
Raise truck passing and parking rules for safetyHOA BOD with PrilandNov 30, 2026
Get Priland's response on the elevated area in Phase 2HOA BODDecember 2026

5. Concerns System

Discussion

  • The HOA created a concerns system with the PMO for action tracking and timelines.

  • Concerns are being reported but not acted on, which has been disappointing. A better process with the PMO is needed.

Action ItemResponsibleTimeline
Agree with the PMO on response times and regular status updates for logged concernsHOA BOD with PMONov 11, 2026

6. Drainage and Grass Near the Detention Pond

Discussion

  • The drainage near the detention pond is sometimes clogged with dirt during rain. A homeowner asked who is in charge of maintaining and clearing the drainage.

  • Grass is growing in front of Block 3 along the detention pond area. Sir Lourd suggested cementing the area so grass will not grow back.

  • A maintenance officer needs to be identified.

Action ItemResponsibleTimeline
Confirm who is in charge of drainage maintenance and clearingHOA BOD with PrilandTo be set
Assess the suggestion to cement the area in front of Block 3HOA BODTo be set
Identify a maintenance officerHOA BODTo be set

7. Dog and Stray Cat Issue

Discussion

  • November 11: the City Veterinary Office will do impounding and will speak with the dog's owner to resolve the issue.

  • If this does not work, homeowners will sign a petition requiring the dog to be leashed.

  • Stray cats: ask the City Veterinary Office if they can also collect stray cats.

Action ItemResponsibleTimeline
Coordinate the November 11 visit with the City Veterinary OfficeHOA BODNov 11, 2026
Prepare a petition if the intervention failsSecretaryAfter Nov 11
Ask the City Veterinary Office about stray catsHOA BODNov 11, 2026

8. HOA Group Chats

Discussion

  • Homeowners are encouraged to join all HOA channels: the Main group chat, Marketplace, Concerns, and the Facebook group.
Action ItemResponsibleTimeline
Share the links to all group chats and the Facebook groupSecretaryNov 9, 2026

9. Christmas Party

Discussion

  • A poll will be created for the food: catering, potluck or packed lunch.

  • Food coupons and wristbands will be used.

  • A poll will be created for the date: Sunday, December 13 or Sunday, December 20.

  • Idea: a singing contest.

Action ItemResponsibleTimeline
Create the poll for the food optionSecretaryNov 16, 2026
Create the poll for the date (Dec 13 or Dec 20)SecretaryNov 16, 2026
Prepare food coupons and wristbandsChristmas party committeeBefore the event

10. Adjournment

There being no other matters to discuss, the meeting was adjourned at 6:22 PM.


Prepared by: Jessica Jenn M. Bordios, Secretary
Noted by: Lourd Bernard Mejares, President
Signed copy on file with the HOA Secretary.